Recently we designed and produced a Special Project (100% Grupel), which was sent to Australia to operate as backup power at a Wastewater Treatment Plant (WWTP).
The project consists of:
- 3 generators of 1900kVA (STP) each with MITSUBISHI engine (S16R-PTA) and STAMFORD alternator (S9H1D-B4);
- each generator has a 1200L fuel tank with a holding tank;
- engines equipped with preheating resistors with a circulation pump;
- a remote cooling system;
- generators programmed to operate in parallel mode;
- controller from COMAP brand, by customer’s request;
- the Voltage transformers installed in the alternator are manufactured with integrated fuses, again by customer’s request.