PROJECT DESCRIPTION
The future takes shape in the heart of Luanda in this innovative project, which meets the increasingly cosmopolitan lifestyle of Angolan citizens.
With 345.000 m2 of construction, the Commander Gika Real Estate Project is one of the largest real estate developments in all of Africa.
Grupel ensured the power supply with the installation of six 1600 kVA generators for the office towers. Each generator supplies directly from the alternator up to 15000 V in parallel.
For the residential unit, we supplied three 1500 kVA generators working in parallel. For the shopping unit, the largest in Angola, with 145 000m2 of construction, 215 stores, a supermarket, 6 cinemas, a health club and parking spaces over 2000, we supplied nine generators with 2300 kVA, each supplying up to 15 000V in parallel, directly from the alternator.